Toward renovation of the Bremenstr
  Motosumi Bremenstr. Shopping District located in the Western side of the Tokyu-Toyoko-Line Motosumiyoshi Station, which is in Nakahara Ward of the Kawasaki City. Our Shopping District has it's passers-by at a rough estimate 14,000 to 20,000 a day, and we're known as a leading Shopping District also in the Kawasaki City. We declare our basic policy "The Shopping District which customers are able to feel easy and safe." Especially, our learning by exchange with the City of Bremen, we advocates "The Environmental problem which Shopping District tackles in." As a part of our activities, we carry out special environmental programs as Ecological Bags;-Bring your own Shopping Bags- and One Store One Ecological Activity. And various activities have been performed aiming at a town gentle to global environment.

Under these circumstances, the mall enterprise undertaken by 1989, passed for about 15 years, breakage of a street was found. With the cause of breakage of street, some troubles appeared in passing of a pedestrian and a bicycle. So we determined and inquired to renovate the street, based on financial support by the country, the prefecture, and the city.

In October, 2003, partners and a design administrator started our "Committee of the Examination for the Motosumi Bremenstr. Shopping District's renovation" over three years works with the questionnaire to a customer and shops. In order to tell the contents of examination to the neighborhoods including partners, the bulletin "Motosumi Bremenstr. Shopping District's renovation news" was issued. Furthermore, the explanation meeting was also held to the measure for obtaining an understanding to cooperation.

       
 
"Committee of the Examination for the Motosumi Bremenstr. Shopping District's renovation"
-From the Examination to the Completion of the renovation-
 
[Apr. 2003 - Mar. 2004]
May 2003 General meeting resolution
(the affair of renovation)
Oct. 2003 1st. Renovation Committee
Questionnaire to customers
Questionnaire to partners
Dec. 2003 2nd.Renovation Committee
Jan. 2004 3rd.Renovation Committee
Feb. 2004 4th.Renovation Committee
Mar. 2004 5th.Renovation Committee
[Conclusion of the basic ideas for renovation]
[Apr. 2004 - Mar. 2005]
Apr. 2004 1st.Renovation Committee
[Meeting for the renovation's report]
May 2004 2nd.Renovation Committee
Jun. 2004 Designing Works
Jul. 2004 3rd.Renovation Committee
Sept.
2004
4th.Renovation Committee
Oct. 2004 5th.Renovation Committee
Dec. 2004 6th.Renovation Committee
Jan. 2005 7th.Renovation Committee
Mar. 2005 8th.Renovation Committee
[Extra-General meeting]
*Determine Contents of an enterprise/Entrepreneur
/Construction contractor
*Conclusion of the Ecology plan/Informational master plan
[Apr. 2005 - Nov. 2005]
Apr. 2005 1st. Entrepreneur adjustment meeting about construction
[Nakahara Police Station/Nakahara Ward Construction Center/Bus Entrepreneur]
2nd. Adjustment meeting
May 2005 3rd. Adjustment meeting
Explanation meeting for construction [twice]
Jun. 2005 4th. Adjustment meeting
Jul. 2005 5th. Adjustment meeting
Grant of a subsidy from the country and prefecture
Construction start
Aug. 2005 6th. Adjustment meeting
Nov. 2005 Renovation Completed

 

     
Next